Our final phase of repaving the North Roche Harbor Road system starts 5/5/25. Signs are going up to notify drivers of the project and its work hours. The contractor is expecting the paving work to occur on these days in the following areas:
Tuesday May 6 and Wednesday May7: Brooks Lane and Davison Head Drive starting at the east intersection of Brooks/Davison and moving through Afterglow Drive to the intersection of Neil Bay Drive.
Thursday May 8: Tidecrest Way to the east dead end of Neil Bay Drive.
Monday May 12 and Tuesday May 13: Neil Bay Drive starting at Gibbs Lane and moving west to the intersection with Afterglow Drive.
Wednesday May 14: Afterglow Drive from Neil Bay Drive to the stone gates
Thursday May 15: Waters Edge Lane and Claramar Drive to Afterglow
Monday May 19: One half of Afterglow to the airport
Tuesday May 20: Remaining half of Afterglow to the airport
Following the end of the paving work, shoulders and driveways needing gravel to accommodate the new edge will be identified and installed. That work will begin Wednesday May 21 and continue for 1 - 2 weeks.
Should you run into any project related issues the job supervisor at Asphalt NW is Dylan who can be reached at 360-815-1066
Please continue to look for updates on our website www.northrocheroads.com or reach out to the board at nrhra.sji@gmail.com.
--
North Roche Harbor Road Association
nrhra.sji@gmail.com
2025 Proxy Form for mailing in
2024 Special Meeting Notice and Information Packet
2024 Past Email Communication about Special September 21st Meeting
Welcome Packet, History and By Laws
December 2024 Letter to Members with Exhibits
2025 NRHRA Assessment Letter (Submit with payment)
2024 July Letter for Reserve Payment (recalled request)
2024 July FAQs about road construction assessment